1. Home
  2. Articles
  3. Building and renovation
Building and renovation

What a Queensland domestic building contract must contain, and what happens when it does not

Schedule 1B of the Queensland Building and Construction Commission Act 1991 sets minimum requirements for home building contracts above $3,300. This article explains the two levels of regulated contract, the documents the contractor must give, the cooling off right and the consequences of non compliance.

Home building and renovation contracts in Queensland are regulated by Schedule 1B of the Queensland Building and Construction Commission Act 1991. The rules exist because owners sign contracts worth hundreds of thousands of dollars with far less information than the builder has. Knowing what the Schedule requires is the starting point for most building contract disputes.

Two levels of regulated contract

A level 1 regulated contract is for domestic building work with a contract price above $3,300 and below $20,000. A level 2 regulated contract is for work with a price of $20,000 or more, which is the level 2 amount prescribed by regulation. Both must be in writing, dated and signed by or on behalf of each party, and must contain the names of the parties including the contractor’s name as it appears on the licence, the licence number, a description of the work, any plans and specifications, the contract price or the method of calculating it together with the contractor’s reasonable estimate, the date for practical completion or how it is to be determined, and a conspicuous notice of the owner’s right to withdraw during the cooling off period. A level 2 contract must also state the date work will start on site or how that date will be determined, set out the statutory warranties, show a fixed price prominently on the first page of the contract schedule, carry a warning on that page if the price can change, and the contractor must give the owner the QBCC’s Consumer Building Guide before the owner signs. For a level 2 contract the contractor must also give the owner a commencement notice within 10 business days of starting work on site.

Copies and timing

The contractor must give the owner a readily legible signed copy of the contract within five business days after it is signed. Owners who are asked to sign a quote or a one page acceptance and never receive a full contract have a contract that does not comply, and the contractor who proceeds in that position commits an offence and may face disciplinary action by the QBCC.

Deposits

The deposit is capped. For a level 1 contract the maximum is 10 per cent of the price. For a level 2 contract it is 5 per cent, rising to 20 per cent where more than half the contract value is work to be performed off site, such as the manufacture of a kit home or cabinetry. A contractor who demands or receives more than the permitted deposit commits an offence, and the home warranty scheme does not cover the part of a deposit above the cap.

Cooling off

The owner under any regulated contract, level 1 or level 2, may withdraw within five business days after the day on which the owner receives a copy of the signed contract from the contractor. Withdrawal is by a signed written notice stating that the owner withdraws and the provision of the Schedule relied on, given to the contractor or left at the contractor’s address in the contract. If the contractor has not supplied a copy of the signed contract, and for a level 2 contract the Consumer Building Guide, within five business days of the contract being made, the owner may withdraw at any time until five business days after those documents are received. On withdrawal under the ordinary five day right the contractor may keep $100 plus any out of pocket expenses reasonably incurred before the withdrawal, must refund the balance of any deposit, and has no other claim against the owner. The right is not available where the parties had earlier entered into a substantially identical contract for the same work, or where the owner received paid independent legal advice about the contract before signing, or tells the contractor that they did. An owner under a contract for repairs to a home can waive the right by a signed written notice, which contractors sometimes request so that urgent work can start. Owners who have second thoughts about price, timing or the builder’s capacity should act within the five days rather than hoping to negotiate later.

Price, variations and progress payments

The contract price must be stated, together with any allowances for prime cost items and provisional sums, which are estimates for items not yet selected or quantified. Under the Schedule the contractor warrants that those allowances have been calculated with reasonable care and skill, and the contract sets out how they are adjusted when the actual cost is known. Variations must be put in writing and agreed to in writing by the owner before the varied work starts, and progress payments must be directly related to the progress of the work and proportionate to its value. Both are addressed in separate articles.

The statutory warranties

Every regulated contract contains implied warranties that the work will be carried out in an appropriate and skilful way with reasonable care and skill, in accordance with the plans and specifications, with good and suitable materials that are new unless otherwise stated, in compliance with the law, with reasonable diligence, and that a home will be fit for occupation. These warranties cannot be excluded and support a damages claim for defective or incomplete work regardless of what the contract says. Fox Piper does not act in disputes about defective work, which have their own QBCC and insurance pathways, but the warranties remain relevant to contract and payment disputes.

Non compliance

The Schedule provides that a contractor’s failure to comply with its requirements does not make the contract illegal, void or unenforceable, with one important exception: a regulated contract has effect only if it is in writing, dated and signed by or on behalf of each party. Short of that, an owner cannot simply refuse to pay for work properly done on the ground that the contract was deficient. What the owner can do is hold the contractor to the Schedule’s specific rules: a contractor must not take a deposit above the cap, must not start work before the contract complies, must not start varied work before the owner has agreed to the variation in writing, and must not claim a progress payment that is out of proportion to the work done. Each breach is an offence, and the QBCC can also take disciplinary action against the licensee.

Before you sign

Insist on the full contract, check that the price, the start and completion dates and the allowances are filled in, read the Consumer Building Guide, and do not pay a deposit above the cap. If you are already in a dispute, assemble the contract, every variation and every payment claim, because the Schedule’s rules are applied to those documents.

Tell us what has happened through our enquiry form. If we can assist, we will confirm the proposed first step, its scope and fee before you decide whether to proceed.

Sources

The legislation, decisions and official guidance this article relies on. Each link opens the published source in a new tab.

This article is general information about the law as it applies in Queensland and was last updated on 17 November 2026. It is not legal advice and does not take account of your circumstances. Time limits and monetary limits change, so obtain advice on your own situation before acting.

Start an enquiry

Tell us what happened.

A lawyer will read your enquiry and, if we can help, we will reply with a fixed fee for the first step. There is no charge until you decide to go ahead. Everything you send is confidential.

New enquiries
Start with the form so that a lawyer can read what happened before we quote.
Existing clients
(07) 3473 5078, Monday to Friday, 8:30am to 5pm.
Where we act
Anywhere in Queensland, by phone. In person at Level 7, 193 North Quay, Brisbane City, by appointment.
What to have ready
Nothing yet. Once the first step is confirmed we will tell you which documents, photos or messages to send.

Please complete the highlighted fields before sending.

Confidential. A lawyer reads every enquiry before we reply. Documents can be sent once the first step is confirmed.

Thank you. Your enquiry has been received.

A lawyer will read it and, if we can help, we will reply with a fixed fee for the first step and what that step involves. Nothing is charged unless you decide to go ahead.