Variations must be in writing: section 40 and the cost of informal changes on a building job

Queensland law requires a variation to a domestic building contract to be put in writing and agreed to in writing by the owner before the work starts. This article explains the requirements in Schedule 1B of the QBCC Act, whether a contractor can still be paid for an undocumented variation and how owners should respond to a claim.

Few building projects finish exactly as they were drawn. Owners change their minds about tiles, discover they want a bigger deck, or learn that the site needs more excavation than anyone expected. Each change is a variation, and Queensland law is specific about how variations must be documented. Disputes about undocumented variations are among the most common building contract disputes.

The requirements

Section 40 of Schedule 1B to the Queensland Building and Construction Commission Act 1991 requires a variation of a regulated contract to be put in writing. The contractor must give the owner a copy of the variation in writing within five business days after the variation is agreed and, in any case, before the varied work starts. The contractor must not start that work until the owner has agreed to the variation in writing. Under section 41 the document must be readily legible, describe the variation, state the date of the request, give the contractor’s reasonable estimate of any delay, state the change to the contract price or how it will be worked out, and state when any increase is to be paid or any decrease accounted for. An increase cannot be required to be paid before the varied work starts. A contractor who does not comply commits an offence, although it is a defence to the requirement to give the document first that the work was required urgently and it was not reasonably practicable to produce the document beforehand.

The Act does not require both parties to sign the variation. The owner must agree in writing, and an email is enough (Munro v Camdun Pty Ltd [2024] QCAT 452 at [104] to [105]). Many contracts go further. The QBCC’s standard new home construction contract, for example, requires a variation document agreed in writing by both parties before the work begins.

The purpose is to make sure owners know what a change will cost before they commit to it. A text message from an owner saying go ahead may amount to the owner’s agreement in writing, but it does not relieve the contractor of the obligation to provide a variation document that meets the requirements.

The consequence of non compliance

Before 1 July 2015 the Domestic Building Contracts Act 2000 prevented a contractor from recovering anything for a variation that was not properly documented unless the tribunal approved, which required exceptional circumstances or unreasonable hardship. That Act has been repealed and Schedule 1B contains no equivalent rule. Non compliance with sections 40 and 41 is an offence and can lead to disciplinary action, but section 44 provides that a contractor’s failure to comply with the Schedule does not make the contract illegal, void or unenforceable.

QCAT’s appeal tribunal has held that the Act does not prevent a contractor from being paid for an undocumented variation, and that where an owner asks for work outside the contract the ordinary inference is that it will be paid for, at a reasonable price if none was agreed (Boys v Imperial Homes (Qld) Pty Ltd [2024] QCATA 35 at [49] to [53]). QCAT has since applied that approach (Munro v Camdun at [119]).

There are limits. Both parties must have intended to vary the contract, and a contractor who simply does additional work and bills for it afterwards is not entitled to be paid merely because the owner has the benefit of it (Munro v Camdun at [133] to [134]). The contract may itself make written approval a condition of payment. In Thallon Mole Group Pty Ltd v Morton [2022] QDC 224 at [405] the District Court held that a contractor could not rely on estoppel to overcome the owner’s statutory right to a variation in writing, and the Court of Appeal refused leave to appeal ([2023] QCA 250). The position is therefore not fully settled, and a contractor who relies on an informal variation takes a real risk.

Variations the contractor initiates

Not every change comes from the owner. Contractors propose variations when they encounter conditions that differ from what the contract assumed, such as rock, unstable soil or latent defects in an existing structure. The same documentation rules apply, and the owner is not obliged to agree to a variation the contractor proposes. If the owner refuses, the contractor must decide whether the work can be done within the contract or whether the contract makes provision for the situation. Many contracts have specific clauses for latent conditions, which require notice and an opportunity to inspect before the cost can be claimed.

Provisional sums and prime cost items

Adjustments to provisional sums and prime cost items are not variations. They are reconciliations of estimated amounts in the contract against actual cost, and the contract will set out how they are adjusted. Disputes about these items usually turn on whether the original allowance was calculated with reasonable care and skill, which the contractor warrants under the Schedule, and whether the contractor has accounted for the actual cost as the contract requires.

Responding to a variation claim

An owner who receives an invoice for variations should ask for the variation documents and for the owner’s written agreement to each one. If there are none, the contractor has not complied with the Schedule, but that does not by itself mean nothing is payable. If the change was requested and the work was done, the likely outcome is payment of a reasonable amount, and an early negotiated figure may be cheaper than a tribunal dispute about it. Where the variation was never requested or agreed, or the price is unexplained, the owner’s position is much stronger.

For contractors

The lesson for contractors is simple. Document every variation before the work starts, even on the smallest job, and keep copies. A one page variation form completed on site and agreed to in writing by the owner takes five minutes. It avoids an offence, and it avoids a tribunal dispute in which the contractor must prove that the change was agreed and what it was worth.

Tell us what has happened through our enquiry form. If we can assist, we will confirm the proposed first step, its scope and fee before you decide whether to proceed.

Sources

The legislation, decisions and official guidance this article relies on. Each link opens the published source in a new tab.

This article is general information about the law as it applies in Queensland and was last updated on 17 November 2026. It is not legal advice and does not take account of your circumstances. Time limits and monetary limits change, so obtain advice on your own situation before acting.

Start an enquiry

Tell us what happened.

A lawyer will read your enquiry and, if we can help, we will reply with a fixed fee for the first step. There is no charge until you decide to go ahead. Everything you send is confidential.

New enquiries
Start with the form so that a lawyer can read what happened before we quote.
Existing clients
(07) 3473 5078, Monday to Friday, 8:30am to 5pm.
Where we act
Anywhere in Queensland, by phone. In person at Level 7, 193 North Quay, Brisbane City, by appointment.
What to have ready
Nothing yet. Once the first step is confirmed we will tell you which documents, photos or messages to send.

Please complete the highlighted fields before sending.

Confidential. A lawyer reads every enquiry before we reply. Documents can be sent once the first step is confirmed.

Thank you. Your enquiry has been received.

A lawyer will read it and, if we can help, we will reply with a fixed fee for the first step and what that step involves. Nothing is charged unless you decide to go ahead.