Building and renovation

Delays and terminated building contracts

The project is months behind, the site has been quiet for weeks, or a notice has arrived threatening to end the contract. Ending a building contract is a serious step, and getting it wrong turns the innocent party into the one in breach. The first step is a fixed fee consultation on where you stand before any notice is sent or acted on.

Every enquiry is read by a lawyer. If we can help, we reply with a fixed fee for the first step. That step is usually a consultation by phone or in person in Brisbane, and nothing is charged until you decide to go ahead.

  • Extensions of timeA contractor may claim extra time only on the grounds the Act and the contract allow, in writing, within 10 business days of becoming aware of the cause and extent of the delay, and only if the owner approves the claim in writing.
  • Liquidated damagesMost domestic contracts fix a daily amount the owner can deduct for late completion. If the contract is silent, the owner may still claim actual loss.
  • TerminationTermination for breach almost always requires a written notice to remedy the breach, with the period the contract specifies, before the contract can be ended.
  • Non completion coverIf a contractor defaults and the contract is lawfully ended, the QBCC home warranty scheme may cover the cost of completion. The claim must be made within 3 months of the contract ending.

The disputes we see most

  • The completion date has passed, the house is not finished and the contractor says the delay is not its fault.
  • The contractor has stopped work and will not give a date for returning.
  • You have received a notice to remedy breach, or a notice of termination, and need to know whether it is valid and how to respond.
  • You want to end the contract and engage someone else, and need to do it in a way that does not expose you to a claim.
  • A contractor has been locked off the site, or the owner has stopped paying and the contractor wants to end the contract.
  • The contract has ended and there is a dispute about the money: the deposit, work completed, materials on site and the cost of finishing.

Delay under a domestic building contract

A domestic building contract of $20,000 or more must state a date for practical completion, or the number of days from commencement within which the work will be completed. That date can be extended only on the grounds the Act and the contract allow. Under section 42 of Schedule 1B to the Queensland Building and Construction Commission Act 1991, a contractor under a domestic building contract worth more than $3,300 may claim an extension only where the delay was not reasonably foreseeable and was beyond the contractor’s reasonable control, was caused by the owner, or was caused by a properly documented variation. The claim must be made in writing and given to the owner within 10 business days after the contractor became aware, or ought reasonably to have become aware, of the cause and extent of the delay, and the owner must approve it in writing. An owner’s silence is not approval under the Act. Extensions that were never claimed are usually lost. The owner’s remedy for late completion is liquidated damages at the rate the contract fixes or, where none is fixed, damages for the actual loss caused by the delay.

Delay by itself is rarely a ground to terminate. A contract can usually be ended for delay only where time has been made essential, where the contractor has abandoned the work, or where the delay and the contractor’s conduct show that it is unable or unwilling to complete.

Termination

Domestic building contracts almost always set out a procedure for termination. The party relying on a breach must first give a written notice identifying the breach and allowing a stated period, commonly 10 business days, for it to be remedied. If it is not remedied, a notice of termination may then be given. Terminating without following the procedure, or for a breach that is not substantial, is itself a repudiation of the contract, and the other party may accept it and claim damages. Common grounds for an owner include failure to proceed with reasonable diligence, suspension without a valid reason and unlicensed work. Common grounds for a contractor include non payment of a valid progress claim and refusal of access.

After termination, the account must be worked out. The owner is entitled to the cost of completing the work above the unpaid balance of the contract price, together with liquidated damages for delay. The contractor is entitled to be paid for work properly completed and not yet paid for. The owner is entitled to the documents needed to finish, and the contractor to its unfixed materials and equipment. Many of these disputes end in a negotiated exit agreement that deals with all of those items at once.

The home warranty scheme

Where a contractor has defaulted and the owner lawfully terminates, the QBCC’s home warranty scheme may pay for the work to be completed, within limits. The contract must have ended within 2 years of the work starting, and the claim must be made within 3 months after the contract ends. Because the scheme requires a lawful termination, the way the contract is ended matters for the claim as well as for the dispute with the contractor.

Where these disputes are decided

Claims for liquidated damages, the cost of completion and amounts due under the contract are decided in QCAT after the QBCC’s dispute resolution process, with no monetary limit for domestic building work. Decisions of the QBCC on home warranty claims are reviewable within 28 days.

What we do not do

We do not act in disputes about defective work or between head contractors and subcontractors.

What we do

  • Advise you in writing on whether the delay is excused under the contract, what damages are payable and whether a right to terminate has arisen.
  • Draft notices to remedy breach and notices of termination that comply with the contract and the law, or advise on responding to one served on you.
  • Negotiate an agreed exit where that is the sensible outcome, including the handover of the site, plans and certificates and a settlement of the account.
  • Act in the QBCC dispute resolution process and in QCAT on claims for damages, for the cost of completion and for amounts owed under the contract, and on home warranty non completion claims.
The first step is a fixed fee consultation by phone or in person in Brisbane. Tell us what happened using the enquiry form, and if we can help we will reply with the fee for that step before you pay anything. Once we receive payment, we open a file and complete the agreed work.

Common questions

The builder is way past the completion date. What can I claim?

If the contract fixes liquidated damages, usually a daily amount, you can deduct them for each day between the date for practical completion, as extended by any valid extensions of time, and actual completion. If the contract does not fix an amount, you can claim the loss the delay actually caused, such as rent or storage. Delay alone is usually not a ground to terminate unless the contract makes time essential or the delay is so serious that it shows the contractor will not perform.

Can the builder just claim more time?

Only on limited grounds. Under section 42 of Schedule 1B to the QBCC Act, which applies to domestic building contracts worth more than $3,300, an extension can be claimed only where the delay was not reasonably foreseeable and was beyond the contractor's reasonable control, was caused by the owner, or was caused by a properly documented variation. The claim must be made in writing and given to the owner within 10 business days after the contractor became aware, or ought reasonably to have become aware, of the cause and extent of the delay, and the owner must approve it in writing. The contract may add its own requirements. A contractor who did not claim extensions properly during the project often cannot rely on them afterwards, and the delay then counts against it.

How do I terminate properly?

Almost every domestic building contract requires the party ending it to first give a written notice identifying the breach and allowing a stated period to remedy it, often 10 business days. Only if the breach is not remedied can a notice of termination be given. Sending the notices in the wrong order, giving too little time or relying on a breach that is not substantial can make the termination wrongful, which exposes you to a damages claim. We draft the notices and check the grounds before anything is sent.

The builder has sent me a notice to remedy breach. What do I do?

Respond before the period expires, in writing, either by remedying the breach if it is genuine or by disputing it with reasons. Silence is the worst option. If the notice is invalid, for example because the alleged breach is non payment of an invoice for a variation you never requested or agreed to, say so and explain why. Then get advice on the next step.

What happens to the money and the site when the contract ends?

The account has to be worked out: the value of work completed, payments made, materials delivered, liquidated damages and the cost of finishing with another contractor. The party in breach is generally liable for the other's loss. The owner is entitled to the plans, approvals and certificates needed to complete the work, and the contractor is entitled to remove its own plant and unfixed materials it has not been paid for. These issues are best settled in a written exit agreement.

Does the QBCC home warranty scheme cover an unfinished house?

It can. Non completion cover is available where the contractor has defaulted and the owner has lawfully terminated the contract, or the contractor has died, is a company that no longer exists, or is insolvent and has had its licence cancelled, the contract ended within 2 years of work starting and the claim is made within 3 months of the contract ending. Cover is capped and conditions apply, so the termination has to be done correctly. We deal with that process on our QBCC complaints page.

This page is about Queensland law. Updated 17 November 2026.

Start an enquiry

Tell us what happened.

A lawyer will read your enquiry and, if we can help, we will reply with a fixed fee for the first step. There is no charge until you decide to go ahead. Everything you send is confidential.

New enquiries
Start with the form so that a lawyer can read what happened before we quote.
Existing clients
(07) 3473 5078, Monday to Friday, 8:30am to 5pm.
Where we act
Anywhere in Queensland, by phone. In person at Level 7, 193 North Quay, Brisbane City, by appointment.
What to have ready
Nothing yet. Once the first step is confirmed we will tell you which documents, photos or messages to send.

Please complete the highlighted fields before sending.

Confidential. A lawyer reads every enquiry before we reply. Documents can be sent once the first step is confirmed.

Thank you. Your enquiry has been received.

A lawyer will read it and, if we can help, we will reply with a fixed fee for the first step and what that step involves. Nothing is charged unless you decide to go ahead.